Update gantt.md with milestones info
Included a brief explanation about the use of milestones regarding their time location and the code location of the tag with an example.
This commit is contained in:
parent
bb3597614a
commit
4d477d7e96
|
@ -133,7 +133,26 @@ To do so, start a line with the `section` keyword and give it a name. (Note that
|
||||||
|
|
||||||
### Milestones
|
### Milestones
|
||||||
|
|
||||||
You can add milestones to the diagrams. Milestones differ from tasks as they represent a signle instant in time and are identifiedd by the keyword `milestone`
|
You can add milestones to the diagrams. Milestones differ from tasks as they represent a signle instant in time and are identifiedd by the keyword `milestone`. Below is an example on how to use milestones. As you may notice, the exact location of the milestone is determined by the initial date for the milestone and the "duration" of the task this way: *initial date*+*duration*/2.
|
||||||
|
|
||||||
|
```
|
||||||
|
gantt
|
||||||
|
dateFormat HH:mm
|
||||||
|
axisFormat %H:%M
|
||||||
|
Initial milestone : milestone, m1, 17:49,2min
|
||||||
|
taska2 : 10min
|
||||||
|
taska3 : 5min
|
||||||
|
Final milestone : milestone, m2, 18:14, 2min
|
||||||
|
```
|
||||||
|
```mermaid
|
||||||
|
gantt
|
||||||
|
dateFormat HH:mm
|
||||||
|
axisFormat %H:%M
|
||||||
|
Initial milestone : milestone, m1, 17:49,2min
|
||||||
|
taska2 : 10min
|
||||||
|
taska3 : 5min
|
||||||
|
Final milestone : milestone, m2, 18:14, 2min
|
||||||
|
```
|
||||||
|
|
||||||
|
|
||||||
## Setting dates
|