@ -101,12 +101,12 @@ describe('Gantt diagram', () => {
|
|||
title Adding GANTT diagram to mermaid
|
||||
excludes weekdays 2014-01-10
|
||||
todayMarker off
|
||||
|
||||
|
||||
section team's critical event
|
||||
deadline A :milestone, crit, deadlineA, 2024-02-01, 0
|
||||
deadline B :milestone, crit, deadlineB, 2024-02-15, 0
|
||||
boss on leave :bossaway, 2024-01-28, 2024-02-11
|
||||
|
||||
|
||||
section new intern
|
||||
onboarding :onboarding, 2024-01-02, 1w
|
||||
literature review :litreview, 2024-01-02, 10d
|
||||
|
@ -573,7 +573,28 @@ describe('Gantt diagram', () => {
|
|||
`
|
||||
);
|
||||
});
|
||||
|
||||
it('should render a gantt diagram exculding friday and saturday', () => {
|
||||
imgSnapshotTest(
|
||||
`gantt
|
||||
title A Gantt Diagram
|
||||
dateFormat YYYY-MM-DD
|
||||
excludes weekends
|
||||
weekend friday
|
||||
section Section1
|
||||
A task :a1, 2024-02-28, 10d`
|
||||
);
|
||||
});
|
||||
it('should render a gantt diagram exculding saturday and sunday', () => {
|
||||
imgSnapshotTest(
|
||||
`gantt
|
||||
title A Gantt Diagram
|
||||
dateFormat YYYY-MM-DD
|
||||
excludes weekends
|
||||
weekend saturday
|
||||
section Section1
|
||||
A task :a1, 2024-02-28, 10d`
|
||||
);
|
||||
});
|
||||
it('should render when compact is true', () => {
|
||||
imgSnapshotTest(
|
||||
`
|
||||
|
|
|
@ -167,6 +167,38 @@ gantt
|
|||
|
||||
The `title` is an _optional_ string to be displayed at the top of the Gantt chart to describe the chart as a whole.
|
||||
|
||||
### Excludes
|
||||
|
||||
The `excludes` is an _optional_ attribute that accepts specific dates in YYYY-MM-DD format, days of the week ("sunday") or "weekends", but not the word "weekdays".
|
||||
These date will be marked on the graph, and be excluded from the duration calculation of tasks. Meaning that if there are excluded dates during a task interval, the number of 'skipped' days will be added to the end of the task to ensure the duration is as specified in the code.
|
||||
|
||||
#### Weekend (v\<MERMAID_RELEASE_VERSION>+)
|
||||
|
||||
When excluding weekends, it is possible to configure the weekends to be either Friday and Saturday or Saturday and Sunday. By default weekends are Saturday and Sunday.
|
||||
To define the weekend start day, there is an _optional_ attribute `weekend` that can be added in a new line followed by either `friday` or `saturday`.
|
||||
|
||||
```mermaid-example
|
||||
gantt
|
||||
title A Gantt Diagram Excluding Fri - Sat weekends
|
||||
dateFormat YYYY-MM-DD
|
||||
excludes weekends
|
||||
weekend friday
|
||||
section Section
|
||||
A task :a1, 2024-01-01, 30d
|
||||
Another task :after a1, 20d
|
||||
```
|
||||
|
||||
```mermaid
|
||||
gantt
|
||||
title A Gantt Diagram Excluding Fri - Sat weekends
|
||||
dateFormat YYYY-MM-DD
|
||||
excludes weekends
|
||||
weekend friday
|
||||
section Section
|
||||
A task :a1, 2024-01-01, 30d
|
||||
Another task :after a1, 20d
|
||||
```
|
||||
|
||||
### Section statements
|
||||
|
||||
You can divide the chart into various sections, for example to separate different parts of a project like development and documentation.
|
||||
|
|
|
@ -21,6 +21,7 @@ dayjs.extend(dayjsIsoWeek);
|
|||
dayjs.extend(dayjsCustomParseFormat);
|
||||
dayjs.extend(dayjsAdvancedFormat);
|
||||
|
||||
const WEEKEND_START_DAY = { friday: 5, saturday: 6 };
|
||||
let dateFormat = '';
|
||||
let axisFormat = '';
|
||||
let tickInterval = undefined;
|
||||
|
@ -37,6 +38,7 @@ let funs = [];
|
|||
let inclusiveEndDates = false;
|
||||
let topAxis = false;
|
||||
let weekday = 'sunday';
|
||||
let weekend = 'saturday';
|
||||
|
||||
// The serial order of the task in the script
|
||||
let lastOrder = 0;
|
||||
|
@ -63,6 +65,7 @@ export const clear = function () {
|
|||
links = {};
|
||||
commonClear();
|
||||
weekday = 'sunday';
|
||||
weekend = 'saturday';
|
||||
};
|
||||
|
||||
export const setAxisFormat = function (txt) {
|
||||
|
@ -167,7 +170,11 @@ export const isInvalidDate = function (date, dateFormat, excludes, includes) {
|
|||
if (includes.includes(date.format(dateFormat.trim()))) {
|
||||
return false;
|
||||
}
|
||||
if (date.isoWeekday() >= 6 && excludes.includes('weekends')) {
|
||||
if (
|
||||
excludes.includes('weekends') &&
|
||||
(date.isoWeekday() === WEEKEND_START_DAY[weekend] ||
|
||||
date.isoWeekday() === WEEKEND_START_DAY[weekend] + 1)
|
||||
) {
|
||||
return true;
|
||||
}
|
||||
if (excludes.includes(date.format('dddd').toLowerCase())) {
|
||||
|
@ -184,6 +191,10 @@ export const getWeekday = function () {
|
|||
return weekday;
|
||||
};
|
||||
|
||||
export const setWeekend = function (startDay) {
|
||||
weekend = startDay;
|
||||
};
|
||||
|
||||
/**
|
||||
* TODO: fully document what this function does and what types it accepts
|
||||
*
|
||||
|
@ -781,6 +792,7 @@ export default {
|
|||
isInvalidDate,
|
||||
setWeekday,
|
||||
getWeekday,
|
||||
setWeekend,
|
||||
};
|
||||
|
||||
/**
|
||||
|
|
|
@ -267,6 +267,21 @@ describe('when using the ganttDb', function () {
|
|||
expect(tasks[6].task).toEqual('test7');
|
||||
});
|
||||
|
||||
it('should ignore weekends starting on friday', function () {
|
||||
ganttDb.setDateFormat('YYYY-MM-DD');
|
||||
ganttDb.setExcludes('weekends');
|
||||
ganttDb.setWeekend('friday');
|
||||
ganttDb.addSection('friday-saturday weekends skip test');
|
||||
ganttDb.addTask('test1', 'id1,2024-02-28, 3d');
|
||||
|
||||
const tasks = ganttDb.getTasks();
|
||||
|
||||
expect(tasks[0].startTime).toEqual(dayjs('2024-02-28', 'YYYY-MM-DD').toDate());
|
||||
expect(tasks[0].endTime).toEqual(dayjs('2024-03-04', 'YYYY-MM-DD').toDate());
|
||||
expect(tasks[0].id).toEqual('id1');
|
||||
expect(tasks[0].task).toEqual('test1');
|
||||
});
|
||||
|
||||
it('should maintain the order in which tasks are created', function () {
|
||||
ganttDb.setAccTitle('Project Execution');
|
||||
ganttDb.setDateFormat('YYYY-MM-DD');
|
||||
|
|
|
@ -84,6 +84,8 @@ weekday\s+thursday return 'weekday_thursday'
|
|||
weekday\s+friday return 'weekday_friday'
|
||||
weekday\s+saturday return 'weekday_saturday'
|
||||
weekday\s+sunday return 'weekday_sunday'
|
||||
weekend\s+friday return 'weekend_friday'
|
||||
weekend\s+saturday return 'weekend_saturday'
|
||||
\d\d\d\d"-"\d\d"-"\d\d return 'date';
|
||||
"title"\s[^\n]+ return 'title';
|
||||
"accDescription"\s[^#\n;]+ return 'accDescription'
|
||||
|
@ -128,6 +130,11 @@ weekday
|
|||
| weekday_sunday { yy.setWeekday("sunday");}
|
||||
;
|
||||
|
||||
weekend
|
||||
: weekend_friday { yy.setWeekend("friday");}
|
||||
| weekend_saturday { yy.setWeekend("saturday");}
|
||||
;
|
||||
|
||||
statement
|
||||
: dateFormat {yy.setDateFormat($1.substr(11));$$=$1.substr(11);}
|
||||
| inclusiveEndDates {yy.enableInclusiveEndDates();$$=$1.substr(18);}
|
||||
|
@ -138,6 +145,7 @@ statement
|
|||
| includes {yy.setIncludes($1.substr(9));$$=$1.substr(9);}
|
||||
| todayMarker {yy.setTodayMarker($1.substr(12));$$=$1.substr(12);}
|
||||
| weekday
|
||||
| weekend
|
||||
| title {yy.setDiagramTitle($1.substr(6));$$=$1.substr(6);}
|
||||
| acc_title acc_title_value { $$=$2.trim();yy.setAccTitle($$); }
|
||||
| acc_descr acc_descr_value { $$=$2.trim();yy.setAccDescription($$); }
|
||||
|
|
|
@ -109,6 +109,27 @@ gantt
|
|||
|
||||
The `title` is an _optional_ string to be displayed at the top of the Gantt chart to describe the chart as a whole.
|
||||
|
||||
### Excludes
|
||||
|
||||
The `excludes` is an _optional_ attribute that accepts specific dates in YYYY-MM-DD format, days of the week ("sunday") or "weekends", but not the word "weekdays".
|
||||
These date will be marked on the graph, and be excluded from the duration calculation of tasks. Meaning that if there are excluded dates during a task interval, the number of 'skipped' days will be added to the end of the task to ensure the duration is as specified in the code.
|
||||
|
||||
#### Weekend (v\<MERMAID_RELEASE_VERSION>+)
|
||||
|
||||
When excluding weekends, it is possible to configure the weekends to be either Friday and Saturday or Saturday and Sunday. By default weekends are Saturday and Sunday.
|
||||
To define the weekend start day, there is an _optional_ attribute `weekend` that can be added in a new line followed by either `friday` or `saturday`.
|
||||
|
||||
```mermaid-example
|
||||
gantt
|
||||
title A Gantt Diagram Excluding Fri - Sat weekends
|
||||
dateFormat YYYY-MM-DD
|
||||
excludes weekends
|
||||
weekend friday
|
||||
section Section
|
||||
A task :a1, 2024-01-01, 30d
|
||||
Another task :after a1, 20d
|
||||
```
|
||||
|
||||
### Section statements
|
||||
|
||||
You can divide the chart into various sections, for example to separate different parts of a project like development and documentation.
|
||||
|
|
Loading…
Reference in New Issue